| < 2010 | jan | feb | mar | apr | may | jun | jul | aug | sep

SYSTEM FOR SUPERVISION AND REMOTE CONTROL FOR ELEKTROISTRA

KONČAR - Power Plant and Electric Traction Engineering has successfully completed a project of retrofit of SCADA/DMS for the distribution area Elektroistra Pula. The contract was signed two years ago with the HEP ODS Elektroistra Pula and performed as a „turnkey“ project.
Elektroistra Pula distributes electricity in the whole of Istria County in which there are about 210 thousand inhabitants. Modernized system for remote supervision and control will allow better control and management of power grid, analysis and monitoring of load growth and also a more efficient planning and construction of distribution networks.